Sunday, June 14, 2015

Queen's Quay Redevelopment - Problems, Opportunities on Toronto's new "Complete Street"


The new Queen's Quay layout is days away from being completed and fully opened to the public on June 19, 2015. For cyclists, this is particularly welcome news as the closure of the Martin Goodman Trail ("MGT") for years has left a significant gap in the cycling waterfront route. The good news is the new MGT configuration will replace that gap with a new, complete street model that incorporates many of the best practices from around the world. The bad news is there are a couple of major issues that cyclists will have to be aware of to safely travel the route.

1. The Physical Structure

The redesigned Queen's Quay is a multi-modal street that includes:
  • 2 single lanes of auto traffic on the north side
  • A dedicated transit right-of-way
  • A well-signed and complete bike lane that is part of the Martin Goodman Trail Wide pedestrian zones



At every intersection there are mixing zones where different users come together. The designers have used signage, traffic signals and physical materials to let users know how they should behave in these zones and where they should be going.

Below is a picture of the bike marking at one of these mixed zones. There are also going to be painted Blue Boxes for cyclists at every major intersection.


Here are examples of texture and colour used to inform users where they're supposed to go.




And here we have an example of a dedicated bicycle signal.


The changes in material, the markings and the dedicated signals are all meant to tell users where they should go and how they can safely proceed through the intersections.


2. Users Sharing the Road

The physical separation of autos, transit and cyclists seems to work well (well, aside from some motorists who can't quite seem to figure out where they're supposed to be).

Unfortunately, the separation of cyclists and pedestrians is much less clear. As can be seen from the above photo, there are many spaces where pedestrians can freely access the MGT. The design includes a row of trees along the MGT and a physical change in materials from the royal red granite used for pedestrian spaces to the asphalt of the MGT, but these are somewhat subtle differences for a space that is going to have many tourists and family users who may not notice these visual and tactile cues.



An even larger problem is posed by the location and orientation of the 22 benches that have been placed right next to the MGT. Both cyclists and pedestrians will have to be very careful in these areas, as anyone moving even a step or two from the bench is directly in the path of MGT users.



And there are some particular areas where either the signage and pavement markings haven't been completed, or they are inadequate:

1. Service Road entrances


2. The entrance to the Jack Layton Ferry Terminal (where I witnessed 4 near-misses in less than 5 minutes):

Jack Layton Ferry Terminal user conflicts - PicMonkey collage - http://www.picmonkey.com/p/hupA8Drqe8N


We certainly welcome the changes to the Queen's Quay layout and congratulate Waterfront Toronto on completion of a project that should help to bring more people down to the waterfront. But we hope that they will be closely monitoring how users actually behave in these areas and will be ready to tweak any design elements that may prove to be less than ideal in real-world use. As for our advice to Toronto cyclists, its to treat the Queen's Quay MGT like the portion at the Woodbine Beach beach volleyball and change room area - ride slowly, obey your signals, always be under control and be prepared to stop on a dime at any moment.

Note - we'll be posting an update after the MGT opens in order to let you know what additional features have been added and how the MGT is working.


Gerry Brown
Ward 30 Bikes

Thursday, June 4, 2015

Cycle Toronto Email Blast - June 3, 2015 - #BellsOnDanforth & #DanforthLovesBikes

Join us for Bells on Danforth: A pedal-powered parade to celebrate cycling!
Bells on Danforth returns for the fourth annual family-friendlyBells on Danforth
ride across the Danforth. This year the ride reverses direction, starting at the Prince Edward Viaduct and riding east to the crossroads of the Danforth. RSVP on the event facebook page here.
When: Gather at 10:30 a.m. on Saturday, June 6, 2015. The ride leaves at 11:00 a.m.
Start: Prince Edward Viaduct Parkette (west end of Bloor Viaduct, south side, across from Castle Frank station)
Finish: The Crossroads of the Danforth, Danforth Avenue & Danforth Road. The Crossroads of the Danforth BIA will be throwing us a party when we arrive. Hang out, visit one of the local restaurants, or sit for a picnic lunch in the nearby park.
Do you want bicycle lanes on Danforth? Cycle Toronto wants you to sign the Danforth Loves Bikes Pledge!
There is a significant gap in Toronto’s cycling network Danforth Loves Bikes
east of the Don Valley. The Bloor Viaduct helps connect east end cycling commuters out of the core via the protected bike lanes on Sherbourne St. However, the lanes end at Broadview Ave. There are several north-south bike routes east of Broadview Ave but no high quality infrastructure options to connect them.
The City of Toronto is creating a 10-year cycling network plan to be approved by Toronto City Council in 2015. We believe that a pilot project for bicycle lanes on Danforth Ave should be launched in 2016 and that Danforth Ave should be included in the 10-year plan!
Learn more about our Danforth Loves Bikes! campaign.
Do you support bicycle lanes on Danforth? Sign the pledge now!

Hope to see you Saturday!
Jared Kolb
Executive Director
jared.kolb@cycleto.ca






mh

Thursday, May 28, 2015

Advocacy in Action! Keeping Bike Lanes During Construction Projects

It started in early January 2015.

The councillor's office emailed us to ask for some input on a section of the Dundas East bike lanes at Carlaw that would be impacted by a condo development.  The request from the developer was to close part of the bike lane as part of the staging area for the construction of their second phase condo.  A few hundred meters of bike lane closure would result in cyclists having to merge with motor traffic, a safety issue the councillor's office was looking to mitigate.  And this closure would last almost a year, right on the back of the bike lane closure right next door at the first phase of the condo development.  We were potentially looking at a grand total of 2 years of partial lane closures in what is in our opinion, the most heavily used bike lane in the east end.

So, a few ideas were suggested.  Maybe some sharrows and some signage that stated 'shared usage lane single file" would help motorists to stay alert for merging bike traffic.   But then one of Ward30bikes' members Vivien suggested something much safer.  On the south side of Dundas, directly across from construction  site were 4 on street car parking spots.  If we could temporarily remove those 4 parking spots during the construction period and restripe the road, all the lanes could shift south and remain open.  Bike lane, car lane, car lane, bike lane.    This sounded MUCH better than:  merged bike/car lane, car lane, bike lane, parking spots.

So we proposed it, and to our delight the councillors office and Streetcar developments were supportive.  A site visit was organised in February for us and also bringing in city staff.  The site visit went very quickly.  All parties agreed it could be done.

So, with a plan, things were underway.  Council approvals happened, but then we had to wait.  Mostly for weather conditions to improve to do the scraping and painting, but there were also some misunderstandings between city departments thinking it couldn't be done, but then in fact it could.    The group of us working on this really were hoping this would have happened in April, but such is life with city processes sometimes.

Eventually it did happen, and in early May our bike lane re-opened (to lots of cheers from us!).

A big thank you to Paula Fletcher's office for being pro-active on dealing with cyclist safety issues and asking for our input at the beginning.  Also a very big thank you to Streetcar Developments for being open to our ideas for keeping cyclists safe during their development work.



This story was picked up in the Beach Mirror: http://www.insidetoronto.com/news-story/5646319-dundas-bike-lane-re-opens-in-leslieville/

But also, just today PWIC voted unanimously in favour of improving cyclist safety during construction. Thank you to  Councillors Joe Cressy, Mike Layton, and Mary-Margaret McMahon for championing this at the committee.